July 2002

Contents : The curse of assumption:

Hello

We all get caught out by assuming we either believe something to be a fact or that something must be true because everyone says it is a fact. Or in my case, I know things about building houses that I assume everyone thinking of building would know. Then I'm surprised they don't know and have to remind myself that while I do this every day, most people probably only build a new house once in their lifetime.
So this month I've chosen a couple of topics where this curse of assumption catches us all out from time to time.

  1. Aluminium exterior window and door joinery are maintenance free
  2. Getting mortgage money and how or when payments for a building project are made.

1. Maintenance free aluminium window joinery

Most people building a new home would naturally believe that aluminium exterior window and door joinery are maintenance free. Sorry but they are not. That's the curse of assumption. As I did last month, I'm going to refer to a BRANZ Bulletin.

No material used in building is completely maintenance free, but some materials require less maintenance than others. One of the reasons for the popularity of aluminium joinery is the lower maintenance requirement when compared to timber joinery.

The consequences of poor maintenance of aluminium joinery tend to be less severe than for timber joinery, but even aluminium joinery requires some maintenance if its appearance and function are to be maintained.

Maintaining a good appearance is not actually a big job. Sometime we lose sight of the fact that the houses we live in should just be financial investments as they are made from just bricks and mortar and will be sold some day, hopefully for a handsome capital gain. Because we attach emotional strings to our investment and call them home, and home being the place to relax and shack off the day's stress, too often the last thing we want to do in our free or leisure time is wash aluminium windows, clean spouting, touch up chipped, cracked or faded paint. But by neglecting small maintenance issues as they arise can and often does adversely affect our investment. Remember, sooner or later you will sell your home/investment/liability?

This is the BRANZ recommendation to clean and maintain aluminium joinery;

  • Remove loose deposits with a clean wet sponge.
  • Use a soft, non-abrasive brush with a mild detergent to remove more stubborn deposits of salt and dust.
  • Always rinse thoroughly with fresh, clean water.
  • Weathered areas can have the surface restored using a special cutting cream designed for this purpose (ask your local window manufacturer, you'll find them in the yellow pages)
  • Paint splashes or sealants can be removed from powder-coated surfaces with methylated spirits, turpentine, white spirits or ethyl alcohol.
  • Do not use strong solvents, such as lacquer thinners, as these will damage the powder-coating, although the damage may not show until months later.
  • Small scratches and chips can be repaired using a special kit from the window maker

.An important maintenance issue for sliding doors and windows is the cleaning of tracks. Dirt such as leaves, sand or other debris should be cleaned out regularly as these will interfere with smooth operating and may also block up drainage outlets. Drainage holes need to be kept clear. This is of particular importance where laminated glass or insulated glazing units are used.

If looking after you investment is important to you, whether you are building a new home or just maintaining your existing, then I strongly recommend you invest in this BRANZ Bulletin… or phone the office and I'll gladly answer any questions or queries you may have.

2. What information does the bank want before giving a mortgage and how are the payments made when building a house.

This is one area where I have suffered from the curse of assumption. Some how I just believed that everyone would know the steps you must take to satisfy the bank before they would agree to hand over the cash, and how payments are made to the builder.

Firstly, the bank is going to want to know four things; 1) How much do you want to borrow. 2) Do you have the means to pay the money back. 3) After completion of the project is there enough value in the asset to secure the bank's investment if something goes wrong and the asset has to be sold to repay the mortgage (i.e. you don't over capitalise you property , or in layman's terms - money spent on the house and land is way more than what it would ever be sold for. 4) Can the bank get security over the loan by having the first mortgage and holding in their position the Certificate Of Title over the property on which the house is to be built as well as maybe other assets (usually properties) that may be owned by the mortgagee to cover the amount of money being borrowed.

The bank is going to want to know all of this in advance but what I want to discuss is how you go about getting the costing information for the house.

You start by deciding what you want to build and how much you want to spend. Obviously, a brief visit to your bank manager to find out how much you can borrow can save a lot of time and expense.

Then have the plans prepared based on giving firm instructions to the architect or designer that the cost of the project has to cost around $?????, give or take 10%. It's at this point that a lot of good-will between designer and owner must take place. What do I mean by that? Well, a competent designer should carry out a brief procedure of finding out what size the owner wants and what quality of materials they want to build with.

Very quickly, with this information the designer should be able to guide the owner by calculating estimated costs based on size (an average m² rate). An unethical designer may choose not to do this for fear of losing the design project and purposely estimating low, or if the designer does give a reasonably accurate estimate the figure is beyond the means of the client, and the client may choose to try someone else to get a cheaper price. Remember, some designer's fees are based on a percentage of the value of the completed building, so a more expensive house will be a financial advantage to the designer. My advice, be up front and honest, tell your designer to do the same and work as a team with your designer.

With a completed set of plans, and maybe a quote or two to build, this information will be forwarded on to a registered valuer (that's assuming the quote is within the limits of what the owners expected). The registered valuer will prepare a report for the owner to take to the bank. This report will contain a projected value of what the property will be worth once the proposed house is built. The bank will use this information to either reject the application for a mortgage or structure a package to satisfy both the bank and the owner.

Progress payments are paid to the builder usually in instalments as listed below. And in most cases where money is being borrowed for a proposed building, the bank will insist that a registered valuer inspects progress or that stages of the building have been completed before money is released to the owner to pay the builder. What usually happens is that the bank places the money in the owner's cheque account so a cheque can be written out to the builder. However, in some cases where the banks feel that the builder may not get paid because the owner looks like they may decide to buy ten thousand Lotto tickets or take a holiday, the bank may decide to deposit the money directly into the builder's account.

When we (Moss Brothers Housing) build we always use the standard Master Builders Housing Contract Agreement. Progress payments are made in the following way:

  • 10% deposit. This is paid the same time that the contract is signed and agreed to.
  • 15% on completion of the foundation.
  • 30% on completion of the roof framing.
  • 15% on completion of the fitting of the doors, windows and exterior sheathing.
  • 10% on completion of all interior wall linings.
  • 20% on completion of the contract.

This formula is not set in concrete and can be altered to suit all parties.

The last 20% of the contract money is paid at the same time as all or both parties agree the project is complete. At this point the Completions Certificate is signed and the owner can take possession. There are no retention monies held back until after the maintenance period, as used to happen years ago, because today we have in place the Master Builder 5 Year New Home Guarantee. The Master Build Guarantee is usually sufficient security for most owners and banks.

Sometimes the owners wish to take possession before the last bits and pieces are complete. The only way to do this is sign the Completions Certificate, meaning the project is complete but subject to the following items being complete, then make a list and both parties will sign and date. The owner must remember that they must still pay all contract completion monies at this point and before taking possession. If they feel uncomfortable handing over all monies, both parties can agree to lodge the money in the Trust Account of the Master Builders.

I have done my best to describe the procedure here in writing the best way I can. If I have made it as clear as mud for you and created more questions than answers then you can either free phone me (the 0800 number is listed below) or email me with the best number to phone you on, giving a time and day and I'll do that.

By the way; we have fantastic computer technology that allows you to see your proposed house finished before we print the plans. All plans are now prepared on computer. Once we have them in the computer you can see exactly what your proposed house looks like before we finalise the plans. We'll even be able to take you on a journey around the outside of your new home, looking at it from all angles.

Regards
Julian Moss